Supernode Stage 2 Completes Construction and Commences Operations

News

28 July, 2026

Stages 1 and 2 are now the largest operational BESS in Australia’s National Electricity Market

Brisbane – 28 July 2026  – Quinbrook, a specialist investment manager focused exclusively on delivering the infrastructure needed for the energy and digital transitions, today announced that Stage 2 of its Supernode battery storage project in Queensland has successfully completed construction and commenced commercial operations. Moreover, Stage 3 has also reached financial close on an additional A$469 million in debt financing, bringing total project financing across the Supernode complex to c. A$1.2 billion.

The first two stages of Supernode are now operational which completes delivery of the Origin-contracted stages marking another successful milestone in the project’s development.

Stage 2 is now operating under a long-term tolling agreement with Origin Energy. Stages 1 and 2 have a combined capacity of 520 MW / 1,858 MWh. The first two stages were delivered in line with the original completion schedule despite the many complexities of constructing and commissioning utility-scale battery storage systems in Australia’s National Electricity Market (‘NEM’). Stages 1 and 2 together comprise the largest operating BESS in the NEM today.

Supernode Stages 1 and 2 were delivered in partnership with Quinbrook affiliate Private Energy Partners, with the partnership continuing through construction of Stage 3.

Stage 3 also reached financial close on a A$469 million debt financing package. The financing builds on the January 2025 financing of Stages 1 and 2 with continued backing from Commonwealth Bank of Australia, MUFG and Deutsche Bank, alongside new lending partners DNB and Rabobank. Financing terms improved on the earlier facilities, reflecting Quinbrook’s growing track record in developing, constructing and financing utility-scale battery storage coupled with the strength of Stage 3’s 15-year offtake agreement with Stanwell Corporation.

Achieving commercial operations for Stage 2 means we've successfully delivered both Origin-contracted stages on schedule, an outcome we're incredibly proud of given the complexity of commissioning utility-scale battery storage projects in Australia.

With Stage 3 now fully financed, we've reached another important milestone in Supernode's continuing development. The ongoing support of our banking partners also reflects confidence in the Supernode project, our delivery track record and the long-term outlook for battery storage in Australia.

Tim Horneman

Managing Director and Australia Regional Lead

James Allan, Senior Director, Quinbrook, said Supernode’s value extends well beyond the battery currently under development.

From the outset, Supernode was designed as more than just a battery storage project. Its unique location at the heart of Queensland's transmission network makes it ideally placed to support the state’s transitioning power system well into the future. The site also has capacity for a further 520 MW of expansion, which could include battery storage, data centres or a combination of both. Opportunities to develop infrastructure at this scale, in such a strategically connected location, are exceptionally rare.

James Allan

Senior Director

Quinbrook was advised by ICA Partners (financial), King & Wood Mallesons (legal) and Aurecon (technical). The lenders were advised by Allens (legal), RINA (technical), Lockton Companies Australia (insurance), KPMG (tax) and Aurora Energy Research (market).

About Quinbrook

Quinbrook is a specialist investment manager focused exclusively on the infrastructure needed to drive the energy and digital transitions. Led and managed by a senior team of energy industry professionals, Quinbrook is an accomplished asset creator and business builder that conceives, develops, constructs and operates a diverse array of innovative infrastructure projects and growth platforms. Since its founding in 2015, Quinbrook has invested in over 40 GW of energy infrastructure assets and businesses representing a total transaction value exceeding USD 27 billion spanning large-scale renewable power generation, biofuels production, long duration storage, hyperscale data centre infrastructure, AI powered asset optimisation, grid support and flexibility solutions in North America, the UK/Ireland and Australia.